tate and lyle

Forefront Utilities diverted an overground, high pressure 18” gas main.  The client faced significant operational costs by either switching to an alternative fuel supply or shutting down production, while the gas main was 40 feet above ground.

Our specialist drilling team was deployed for the job. By drilling and line stopping the live gas main, it was successfully diverted with no interruption of supply or additional costs to the client. The operation took three months to complete.